Asphalt Base has
been completed on almost all the streets in Sector A of Phase-VIII
ie from 15th Street till 41st Street.
Work on Zulfiqar
Streets however will be executed by separate contractor
Al-Murtaza
Commercial Area
Work has commenced
in June 2009. Work on construction of internal streets and lying
of water supply lines is in progress.
SECTOR-B
Embankment
work is almost 95 percent completed.
Laying of sewerage
line using FC pressure pipes is in progress
As per decision
of EBM this partial area of Sector B ie between Kh-e-Ghalib
and Kh-e-Faisal is expected to be opened for construction by
Dec 2009. Contractor M/s NLC is already working on this project
to meet the dead line of Dec 2009.